Sonora Resources flow charts meanings seem GIGO

The  2  time lines  are based on  near term start for high value mostly based  on  a partner  cash input  we  know  was  rejected   due  to too little for Mexus  holders but  still SOMETHING must  be  above  current  4  cents .  That  plan starts  placer now  in June  making 1837 oz  total  by  Jan.  Milling  begins  August  making  6,819 Au oz  and 39,778 Ag.  NO heap leach at  all until after  June  2105  with initial  15K tons ( 500 day) working up to Dec  at   5,166  day ( 155,000 in Dec).  Using   $1300 and  $20  2014 revenue  $10,164,700 gold  and $795,560 silver little over   $12 million or .046 each of  258.6 mil shares.  Can BUY  it  for  .04  today.  Makes  a  PE of   under ONE! I’d expect  a  1,000% gain those  annual figures with PE 10 or  .46 for  a  base.

Lower  value chart seems current  go alone  and  slow no real  cash  influx.  Placer  begins   August with low 3,100 tons  up to 9,300 by Dec .  Mill operates  in Oct  from  1,550 tons to Dec  2,375.  No heap until Sept   2015 with 15,000 tons. Totals  figures seem to make no sense listing  placer  grade in  oz and  recover  in grams , 30 times  less. Placer grade  is  way off  using .40 oz when  .042 oz  seems  right  like  the  High chart  value.  Works  out  to  milling gold $3,367,000, silver  $335,937 and placer $1,506,960 total  $5,209,897.  2 cents  a  share revenue.  PE now  of  2  and  new base  of  .20  with PE 10.   Even  there   PPS .04  just  silly.  Split  difference and   has  to work to a  33 cent  share  right  now with a  partner  or  go alone slower.  8

4 thoughts on “Sonora Resources flow charts meanings seem GIGO”

  1. Hi Eight. You mentioned the possibility of a go alone for Paul, assuming the unlikely event that he does not get a satisfactory offer from the remaining parties. Do you know if the current activities at the Rancho are setting up for this possibility? Thanks!

    1. Low chart corrected for dumb stuff seems the path being taken. No change but time. That’s Placer ASAP, mill operating next and ALWAYS was no leach considered until built out next year. Really not much time lost at all that’s the case. NEEDS money but can do it on the shoestring. $1300+ POG will hep! 4 oz/100 ton placer day meets payroll, by Dec 300 tons 12 oz/day gets to some build out profit. Running mill gets things moving along
      Been so long off RB now some have almost stopped cursing me. SOME. Silent near son Dax says it well. “Any you’se been there?” Only 6 I know shared the drive. Pretty telling figure blowing noise considered. Wanna know the PPS reason? Ignorant leading the dumb! 3 blind men and the elephant. Wall, tree, snake. None and all. Need to see it to believe. 8

      1. Thanks Eight, appreciate the feedback. I knew Paul did have a Plan B worked out, just was curious if he was currently moving forward at the Rancho since the negotiations are taking a little longer than expected.

        1. His rejection meant rejection. Sure he knows redemption is turn out metal and have other shareholders involved blow stack at woulda coulda story all out in due time. Meantime back at the Ranch still just June. Half ’14 to go. 8

Leave a Reply